MARA and Riot sold 60,845 Bitcoin. Where did the cash go?
MARA Holdings and Riot Platforms have reported roughly $4.5 billion in proceeds from the sale of 60,845 Bitcoin in 2026, with the miners using their holdings to help pay down debt and finance power and data center projects.
- MARA sold 13,597 BTC after September, raising about $1.1 billion as it repaid Bitcoin-backed loans.
- Riot sold 20,264 BTC through September, more than four times what it mined over the same period.
- The new Long Ridge notes would bring the principal in that series to $785 million.
MARA’s Nov. 17 filing gives the latest update on that financing. Its U.S. subsidiary priced $185 million of senior secured notes issued by Long Ridge Energy LLC in connection with the pending $1.5 billion acquisition of Long Ridge Energy & Power.
The notes carry an 8.75% coupon and mature in 2032. MARA expects the offering and acquisition to close together on Nov. 27, subject to customary conditions.
MARA’s Bitcoin sales helped clear acquisition debt
MARA’s third-quarter shareholder letter says the company sold roughly 26,984 BTC for $1.9 billion in the first nine months of the year. It sold another 13,597 BTC after September at an average price of $81,039. The later sale was equivalent to around 40% of the 34,012 BTC MARA held at the end of September.
As crypto.news previously reported, MARA’s Bitcoin-backed financing included $600 million in new borrowing for Long Ridge and $150 million to refinance an existing facility. The company repaid the full $750 million after September, releasing the Bitcoin it had pledged against those loans.
MARA began allowing sales of newly mined Bitcoin in 2025 and expanded that policy this year to cover coins it already held. The shareholder letter says future sales can provide cash for capital projects and other initiatives, depending on market conditions and the company’s spending priorities.
The new notes would sit alongside $600 million of existing Long Ridge notes with the same coupon and maturity. The two issuances would carry roughly $68.7 million in combined annual coupon payments on $785 million in principal, including about $16.2 million from the new notes.
MARA said it plans to use the proceeds and cash on hand to help pay for the acquisition, repay part of Long Ridge’s existing debt and cover transaction expenses.
Long Ridge operates a 485-megawatt natural gas plant in Hannibal, Ohio, alongside an existing MARA mining site, according to MARA’s quarterly filing. MARA sees the site as a potential campus for high-performance computing and says it has received formal indications of interest from prospective tenants. The Federal Energy Regulatory Commission approved the acquisition on Nov. 4.
Riot sold more Bitcoin than it mined
Riot’s quarterly filing shows it raised $1.48 billion selling 20,264 BTC through September, primarily to fund data center development and fully repay a $200 million credit facility. Riot mined 4,697 BTC over those nine months, putting its sales at about 4.3 times production. Its holdings fell from 18,005 BTC at the start of the year to 2,418 BTC on Sept. 30.
The sales put MARA and Riot at the top of a Lookonchain ranking of sellers published Nov. 10. The two miners accounted for roughly 56% of the 108,247 BTC sold by the 14 listed companies in that tally.
Riot said it expects to sell substantially all the Bitcoin it mines for the time being to pay for data center development, other projects, operating costs, and working capital.
In October, the company completed a transfer of Bitcoin custody from NYDIG to BitGo. Its agreement with NYDIG ended after the transfer on Oct. 29, with no early termination penalty.
Riot filed its nine-month cash flow statement with no proceeds from its at-the-market stock offering, compared with $199.6 million in the same period a year earlier. It recorded $226 million in purchases of property and equipment, including construction in progress, during the first nine months of 2026.
Anthropic leases Riot’s Corsicana campus
Riot identified Anthropic as the tenant in its quarterly filing. The 15-year lease covers 910 megawatts of critical IT capacity at the Corsicana campus in Texas. Riot’s earnings release puts the initial contract value at around $28 billion, including rent increases written into the agreement.
Riot estimates it will need $5.5 billion in capital for the project and expects average annual rent of approximately $1.8 billion over the initial term.
Riot signed the Corsicana lease on Oct. 28, and it took effect on Nov. 4. The filing says Riot will provide land, powered pads, and related infrastructure. It expects to begin delivering capacity in June 2027 and have the full 910 megawatts available in July 2028.
Riot’s mining revenue fell to $116 million in the September quarter from $160.8 million a year earlier. The quarterly filing lists an average production value of $70,855 per coin and a mining cost of $78,805 after equipment depreciation. Before that depreciation charge, Riot reported a cost of $39,265 per BTC.